Parking lot improvement project update

The quarry operators strike has ended, allowing the parking lot project to move forward with an updated schedule:

  • August 1: Grinding operations on the front portion of the parking lot to remove all remaining original asphalt
  • August 2-3: Fine Grading operations and rolling¬†
  • August 4-5: Hot Mix Asphalt Binder and Surface courses installed
  • August 8 or 9: Install Surface course to rear lot
  • August 10: All striping and signage completed
  • August 11: ¬†All areas open to patron and public parking